Welcome back 👋

Here is what is happening on the VISDELTEX line today.

Showing matches for · 0 results
Ready · Press Start to run the shift

Single-shift production simulation
on the VISDELTEX fiberglass line

Discrete-event production model running over a single 8-hour shift. Each cycle of 62 s feeds the Extension → Sewing → Palletising flow with weighted scrap routing.

USDC Scene
VISDELTEX.usdc
FPS 59.9
RTX 2.0
Produced
0u
Finished
0u
Scrap-eq.
0u
Cycle
62s
Shift 1 · Hour 0 of 8 (single working day) 0% elapsed
82%
efficiency
Material Efficiency
Useful output
vs total input
Finished380 u
Scrap-equivalent84 u
47.6u/h
finished
Throughput
Output rate
per simulated hour
Total flow58.06 u/h
Theoretical58.06 u/h
16.94
per good unit
Unit Cost
Total cost split
over finished output
Total / shift€ 6,440
Energy / shift37 kWh

Production Flow

top-down · Omniverse scene
Extension · 62s
Sewing · 62s
Palletising · 62s
Scrap · w=18

System-level flow

Three aggregated modules with weighted scrap branch after Extension.

1
Extension OP_Extension_Module
464 u
Scrap branch weight = 18
84 u
2
Sewing OP_Sewing_Module
380 u
3
Palletising OP_Paletizado_Module
380 u

Production Modules

deterministic cycle · 1 replication
FULL-STREAM · 100%
Extension
material loading · cutting · 4-layer layup
Cycle62 s
Processed464 u
Scrap branch18%
Utilisation100%
USEFUL-FLOW ONLY
Sewing
horizontal & vertical sewing
Cycle62 s
Processed380 u
Inputpost-scrap
Utilisation82%
FINAL HANDLING
Palletising
final handling & output
Cycle62 s
Finished380 u
Output47.6 u/h
Utilisation82%

Output Split

finished vs scrap-equivalent

82%
useful
Finished output
380 u
Scrap-equivalent
84 u
Total produced
464 u

Throughput over the shift

cumulative units · finished vs scrap-equivalent · 8 h

Finished
Scrap-eq.

Engineering Assumptions

editable values · drive cost, energy & CO₂ calculations

PROXY · NOT LCA
€/u
€/kWh
kg/kWh
kW
kW
kW
€/h
Operational specification · VISDELTEX line

Production Parameters

Nominal operational specifications of the production system. These parameters define the baseline behaviour used as reference for scenario evaluation.

VISDELTEX fiberglass layup line — factory render

VISDELTEX Production Line · NVIDIA Omniverse

Complete fibreglass layup, ultrasonic cutting and palletising system. Three aggregated modules: Extension → Sewing → Palletising.

~30 m total length 4-layer fiberglass layup 62 s cycle · 58 u/h

Operational Parameters

baseline configuration · deterministic
Cycle Time Nominal s / piece
62 s
Total time required to produce one unit or batch from system entry to output. Includes processing, transfers and waiting.
deterministic
Throughput Nominal pieces / hour
58.06 u/h
Amount of product produced per unit of time under nominal operating conditions. Computed as 3600 / cycle time.
3600 / 62
Maximum Capacity pieces / hour
58.06 u/h
Theoretical maximum production of the system or limiting station under ideal conditions. Limited by the slowest module.
bottleneck-balanced
Transfer Time between stations
0 s
Time required to move material from one station to the next. Set to zero in the deterministic baseline configuration.
setup = 0 s
Buffers Available FIFO accumulation
2 × 10 u
Intermediate buffers and their capacity. BUF_After_Extension and BUF_After_Sewing, each holding up to 10 units.
yes · 10 u each
Operating Mode process behaviour
Continuous · Async
How the process flows: continuous or batch, and whether stations operate synchronously or asynchronously.
DES · MoveStrategyWeighted

Visual Performance Analysis

module behaviour breakdown

Cycle Time per Module

seconds per piece · all modules balanced

Module Utilisation

working time fraction

Full
Post-scrap

Capacity Utilisation

observed vs theoretical maximum

96.5%
capacity used
Observed throughput
57.75 u/h
Theoretical maximum
58.06 u/h
Gap
0.31 u/h · 0.5%

Production Totals · 8h Shift

baseline scenario results

Generated
464 u
total entities by source
Finished
380 u
to Finished_Parts_Sink
Scrap-eq.
84 u
to Scrap_Sink
Throughput
57.75 u/h
observed simulated
Process-level proxies · not full LCA

Sustainability Parameters

Translation of material flow into economic and environmental impact. These indicators are process-level sustainability proxies, not a full Life Cycle Assessment.

18%
scrap rate
Scrap Percentage
Material flow
routed to scrap
Formulascrap / produced
Per shift84 of 464 u
82%
efficient
Material Efficiency
Useful material
vs total consumed
Formulafinished / produced
Per shift380 of 464 u
VISDELTEX sustainability process loop — scrap collection, recovery and reuse

Process Sustainability Loop · VISDELTEX

The production system is designed with a closed-loop material strategy: scrap generated during the Extension phase is classified, collected and routed either for direct reuse (trimmable), external reprocessing (recoverable) or final disposal (residue). This diagram corresponds to the sustainability proxy framework modelled in the dashboard.

Material & Scrap Parameters

editable engineering assumptions
Material Input per Batch kg / batch
125 kg
Total raw material introduced into the system to produce one batch or set of pieces.
assumption · editable
Scrap per Product kg / finished unit
0.27 kg
Total wasted material associated with one finished unit.
derived · 18% routing
Material Unit Cost € / kg
€ 12.00 / kg
Raw material cost per unit of mass. Used to translate material flow into economic impact.
assumption · editable
Scrap Type Breakdown destination classification
Classification of generated waste by destination: trimmable, recoverable or final residue.
Trimmable
40% · 9.1 kg
Recoverable
35% · 7.9 kg
Final residue
25% · 5.7 kg
Trimmable
Leftover material that can be reused directly in the process (e.g. long offcuts).
Recoverable
Material that requires external or internal reprocessing before reuse.
Final residue
Non-recoverable material that must be handled as waste.

Economic & Environmental Impact

direct translation · no LCA

Per-shift impact

baseline scenario · 8h

Scrap material lost
84 u × 0.27 kg/u
22.7 kg
Scrap economic loss
22.7 kg × 12 €/kg
€ 272
Recoverable value
75% of scrap (trimmable + recoverable)
€ 204

Energy & CO₂

operational proxies

Energy / shift
37kWh
≈ 0.097 kWh per finished unit
CO₂ / shift
9.3kg
0.024 kg per finished unit
These are process-level sustainability proxies, not a complete Life Cycle Assessment. Used for relative scenario comparison only.
System breakdown · process stages

VISDELTEX Line Stages

Detailed breakdown of the production system into its eight constituent process stages. Each stage maps to a specific physical operation of the VISDELTEX line.

Stage Map

click any stage for detail
1 Coil feeding
2 Material extension
3 Cutting
4 Stack formation
5 Scrap formation
6 Horizontal sewing
7 Vertical sewing
8 Palletising

Process stage list

Each stage represents a distinct physical operation grouped under one of the three aggregated DES modules.

1
Coil feeding
Extension phase · raw material feed
2
Material extension
Extension phase · layup
3
Cutting
Extension phase · trim to shape
4
Stack formation
Extension phase · 4-layer stack
5
Scrap formation
Extension phase · 18% routing branch
6
Horizontal sewing
Sewing phase · horizontal joining
7
Vertical sewing
Sewing phase · vertical joining
8
Palletising
Palletising phase · final handling

Stage Detail

role in the production flow
STAGE 01
Coil feeding
Coil feed system supplying raw fiberglass material to the line. Maintains continuous input rate to the Extension module.
STAGE 02
Material extension
Layer extension across the work surface. Forms the basis of the 4-layer layup.
STAGE 03
Cutting
Cutting operation defining the final shape. The cutting process is where most of the scrap-equivalent material loss originates.
STAGE 04
Stack formation
Stack formation from the four extended layers. Output of the Extension module routed at 82% weight to the main flow.
STAGE 05
Scrap formation
Scrap-equivalent material generated during the four-layer layup. Routed at 18% weight to the Scrap_Sink.
STAGE 06
Horizontal sewing
Horizontal joining pass across the layered stack. Operates only on the useful material flow.
STAGE 07
Vertical sewing
Vertical joining pass, perpendicular to the horizontal pass. Completes the structural binding of the stack.
STAGE 08
Palletising
Final handling and palletising of the finished stack. Output to the Finished_Parts_Sink.
VISDELTEX · developed by CIDTECH Simulations
inFACTS
DES
Omniverse · USDC